PMP Sample Test 10

Project Management Professional (PMP) – Online Sample Test for Certification exam Preparation

Please enter your email:

1. The project manager of a new project wants to get things started in a positive way with the project team. The project manager wants the team members to get to know one another, to introduce the project team and the project manager to one another, to discuss the objectives and goals of the project, and to identify some of the potential problem areas. This meeting is called a:

 
 
 
 

2. A construction company is being measured by the earned value reporting method. During the project one of the tasks, installing ten elm trees, was completed. The planned value for this task was $4,000, and it was completed two weeks ago. Unfortunately fort he contractor, maple trees should have been planted. The customer insists that maple trees be planted and that the elm trees be removed. As of this time the elm trees are still in the ground, but the contractor has agreed to do the work of replacing them. What action should be taken on the earned value report?

 
 
 
 

3. A project manager is managing a project where there will be a number of persons working together. She wants to enhance the ability of the team to work together and perform as a team. One of the things that she can do to maximize the ability of the team to do this is:

 
 
 
 

4. Lifecycle costing:

 
 
 
 

5. The calculation of the EAC assumes that:

 
 
 
 

6. A project manager is concerned about team building on her project. One of the mandatory things that she must have in order to have good team building is:

 
 
 
 

7. Learning curve theory emphasize that in producing many goods:

 
 
 
 

8. What factors need to be known in order to be able to calculate the ETC?

 
 
 
 

9. An automotive oil change station was receiving complaints that service took too long. A coffee machine and television were installed in the waiting room and the complaints went down. This is an example of:

 
 
 
 

10. Primary outputs from team development are:

 
 
 
 

Question 1 of 10