6. You have been recently assigned to provide an accurate project schedule for a large construction company. You are evaluating the network diagram for the construction project.
Your lead engineer has given you the following estimates for several critical path activity: 30 days (optimistic), 80 days (pessimistic), and 40 days (most likely). Which of the following dates can you commit with approximately a 95 percent confidence level, assuming a beta distribution?