PMP Mock Exam 36

Project Management Professional (PMP) – Online Sample Test for Certification exam Preparation

Please enter your email:

1. You have been recently assigned to provide an accurate project schedule for a large construction company. You are evaluating the network diagrams for the construction project, and are using backward pass calculations to construct the schedule. You are trying to calculate the latest start time for laying the foundation of building. The expected duration for this task is 180 days. The task must be completed within 300 days, while the expected completion is between 220 days. The latest finish date is 270 days. Based on this information, what is the latest start time of this task?

 
 
 
 
 

2. Which of the following best describes resource leveling?

 
 
 
 

3. You are using three point estimating technique to estimate the duration of a schedule activity. Which of the following statements are true given the following data: Pessimistic: 100 days Optimistic: 40 days Most likely: 65 days Average: 68.33 days Variance: 151.38

 
 
 
 
 

4. You have been recently hired to be a project manager at a bio-tech company to develop a new drug to treat pancreatic cancer. The drug has been under development and clinical testing for past 5 years. The FDA is currently reviewing the clinical data in order to determine weather the drug has any serious side effects. If the FDA does NOT approve the drug, the project will be in trouble. This is an example of which type of risks?

 
 
 
 
 

5. Which of the following are NOT used to create the scope baseline for a project?

 
 
 
 

6. You have been recently been assigned to provide an accurate project schedule for a large construction project. You are evaluating the network diagram for the construction project. Your lead engineer has given you following estimates for critical path activity: 30 days (optimistic), 100 days (pessimistic), and 50 days (most likely). What is the standard deviation for this activity, assuming a beta distribution?

 
 
 
 
 

7. Which of the following statements are true regarding the procurement management plan?

 
 
 
 

8. You are the project manager assigned to install the electrical wiring for a 20,000 square foot office building that is currently under construction. You are trying to estimate the costs of this project. You know from past experience that is costs approximately $3 per square foot to properly wire and entire building. As your building will be 20,000 square feet you estimate that the project will cost approximately $60,000. What type of estimating technique did u used?

 
 
 
 
 

9. Which of the following statements are FALSE regarding CPM method?

 
 
 
 

10. Which of the following statements are true regarding funding limit reconciliation?

 
 
 
 
 