1. Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total float. As of today, task one and two have been completed on schedule. How many days of float remain in the schedule for these tasks?

 
 
 
 

2. A task was scheduled to use two persons, full time, and take two weeks to complete. Instead, the project manager was only able to assign one person to this task. At the end of two weeks, the person assigned to the task was 75% complete. What is the cost performance index?

 
 
 
 

3. Resource leveling will generally:

 
 
 
 

4. If a project manager were to make Thanksgiving dinner, two of the activities that might be of concern would be roasting the turkey and baking the sweet potatoes. In order to ensure that these two items will be finished cooking and will come out of the oven at the same time, what type of relationship should he or she use in the schedule between these two activities?

 
 
 
 

5. Schedules are used in many ways. In a project to build a bridge the project manager wants to use a tool that will show the scheduled activities in such a way that it is easy to see when each activity starts and finishes and which activities are taking place at the same time. Which tool should be used?

 
 
 
 

6. Which of the following is true?

 
 
 
 

7. Crashing the schedule means:

 
 
 
 

8. The original schedule (for a project, a work package, or an activity), plus or minus approved changes, is called:

 
 
 
 

9. Which of the following is considered to be a simulation technique?

 
 
 
 

10. The project manager decided to improve the predicted completion date for the project by doing in parallel several of the activities that were scheduled to be done in sequence. This is called:

 
 
 
 